Derek Achong
Senior Reporter
derek.achong@guardian.co.tt
A contracting company has lost its legal battle with the Water and Sewerage Authority (WASA) over outstanding compensation for two contracts for water treatment plants that were terminated almost two decades ago.
Delivering a judgment yesterday, five Law Lords of the United Kingdom-based Privy Council dismissed Waterworks Limited’s final appeal against the public utility.
The legal dispute stemmed from two design and build contracts for water treatment plants in Matura and Yarra.
Around the time the contracts were signed in 2007, the company was informed by the authority of various issues at the proposed sites of both projects.
The authority indicated that it needed to acquire land from a private individual for the Yarra plant and that the Matura plant might need to be shifted from the location initially earmarked for it. It also indicated that Certificates of Environmental Clearance (CECs) from the Environmental Management Authority (EMA) would need to be obtained for both projects.
The company engaged MAAK Technologies Group Inc, a Canadian company, to provide design and construction supervision services for the projects.
MAAK issued quotations for equipment for both plants, which it estimated to cost $15,396,761 for the Matura plant and $11,926,474.88 for the Yarra plant. The company accepted the quotations and issued purchase orders for both.
In 2009, WASA informed the company of its intention to terminate the contracts that had not progressed past the design phase, largely based on its delays.
The company submitted financial claims under each contract, which included 30 per cent cancellation charges for the equipment supply contracts with MAAK.
While the engineer agreed to by the parties approved some claims, he rejected others, including for the third-party compensation charges.
After the company was sued by a lender, it filed a lawsuit against WASA seeking the additional compensation.
Its case was upheld by High Court Judge Trevor Jones, who ruled that the company incurred the significant liability on the expectation that it would have been allowed to complete the contracts.
In June 2020, Appeal Court judges Allan Mendonca, Gregory Smith, and Peter Rajkumar upheld WASA’s appeal.
The judges found that the company’s move to acquire the equipment was premature and unreasonable.
They also found that their colleague was wrong to find that the preliminary designs on which the quotations were based were sufficiently detailed to allow the equipment to be identified and ordered.
In his judgment, Lord George Leggatt ruled that the Appeal Court was right to overturn the judge’s decision.
He agreed that the company rushed to purchase the equipment.
“A prudent contractor would not generally commit itself to purchasing equipment before it is needed (taking into account delivery times) and before the designs to which the equipment must conform have been finalised,” Lord Leggatt said.
He also pointed out that while the purchase orders were issued, MAAK did not take any steps to prepare or ship the equipment before the contracts were cancelled.
Stating that the only benefit the company received for entering into the MAAK contracts was protection from potential price increases, Lord Leggatt said, “In these circumstances, there was nothing to displace, or which was capable of displacing, the inference that it was unreasonable for the contractor to enter into the MAAK contracts when it did.”
He also criticised the company for agreeing to the cancellation charges with minimum performance from MAAK.
“In short, this was a very bad bargain for the contractor to have made,” he said.
The company was represented by Rowan Pennington-Benton and Nicholas Leah. WASA was represented by Ian Benjamin, SC, and Raphael Ajodhia.