Senior Reporter
elizabeth.gonzales@guardian.co.tt
In the last year, several state bodies have been found to be in breach of the procurement law, potentially costing taxpayers almost $166,000 in legal fees. These include three tender evaluation failures similar to those uncovered in the Housing Development Corporation’s (HDC) cancelled $3.48 billion housing programme.
The findings involve the Ministry of Transport and Civil Aviation, Trinidad and Tobago Electricity Commission (T&TEC), Paria Fuel Trading and the Tobago Regional Health Authority (TRHA). All four lost procurement challenges before hearing panels appointed by the Office of Procurement Regulation (OPR).
In the OPR decision documents, Guardian Media found that the panels ordered the public bodies to pay a combined $165,920.83 in legal costs to contractors who challenged their tender decisions - those are costs awarded by the regulator, not fines.
One OPR panel put the rule at the centre of these cases in plain terms: “It was not open for a public body to select a tenderer by a different methodology.”
That warning was issued in a case involving vehicle inspection stickers, not housing. But the rule is the same one cited in the inquiry into HDC’s proposed housing contracts. In three of the four decisions, the regulator found that the public body had failed to follow the evaluation method disclosed to bidders.
The fourth decision, delivered against the TRHA on October 16, found breaches of two provisions of the Procurement Act. Its published order does not set out full written reasons, so the precise nature of those failures cannot yet be compared with HDC’s.
What the HDC report found
The latest rulings came after Guardian Media reported on October 18 the OPR’s detailed findings concerning HDC’s $3.48 billion housing programme. The proposed procurement covered 11 packages of building and infrastructure work at housing developments across Trinidad.
Under the Design-Build-Finance model, contractors were expected to arrange financing for the work. The OPR examined how HDC invited bids, checked the capacity of contractors and arrived at its recommendations for award.
The inquiry found that HDC had asked bidders for three years of audited financial statements but had not set out a scoring method or minimum standard to test whether they could finance the projects. The report said there was no evidence that those statements had been assessed to establish bidders’ financial capacity.
It also found problems with the evaluation of mandatory requirements and changes in how some criteria were applied. In one case, a bidder’s technical score rose from 36.93 to 76.03 after a re-evaluation on April 7. The bidder moved from technically non-compliant to being recommended for award.
The corporation cancelled the procurement on June 17, 2026. The OPR’s inquiry report was dated July 1. The $3.48 billion was the stated value of the proposed packages. It was not a finding that this amount had been paid out.
The OPR subsequently opened a separate investigation into allegations concerning the HDC process. The OPR confirmed on October 8 that its separate probe into allegations of bid rigging and collusion was ongoing.
Price left out of Transport decision
A procurement for vehicle inspection stickers exposed one of the clearest examples of how evaluation rules may have been disregarded.
In June 2026, the Ministry of Transport and Civil Aviation sought bids for the supply and delivery of secure inspection stickers and printing consumables over three years. Four companies submitted bids.
The tender stated that technical quality would carry 70 per cent of the score and the price would carry 30 per cent. It also showed how those scores should be calculated and combined.
JABCO Limited offered the lowest price, approximately 48 per cent below that of Power Cycle Limited, which the ministry recommended for the contract. JABCO challenged the decision.
The OPR found that the ministry’s evaluation committee had chosen the bidder with the highest technical score without calculating the required combined score. In doing so, it left out the 30 per cent financial component.
The hearing panel did not find that JABCO should necessarily have won the contract. Its decision was that the ministry had not followed the rules set out in its own tender documents.
On September 9, the regulator ordered the ministry to terminate the procurement and pay JABCO $43,100 in legal costs. Written reasons followed on October 9.
Confidential terms in T&TEC tender
T&TEC faced a similar finding over a tender to upgrade the first phase of its IP video surveillance system.
Jian Enterprises Limited challenged the re-evaluation of bids after KVR Energy Limited was identified as the proposed successful bidder. The dispute followed an earlier challenge and a confidential schedule of agreed terms between the parties.
The new evaluation used a method under which bidders could receive full marks for a criterion unless a specific failure was identified. The method was not in the original tender documents.
The OPR panel found that a private agreement could not change a State body’s duty to evaluate all tenders according to the published rules. As the written reasons stated: “A private agreement between the procuring entity and a bidder could not alter that requirement.”
The decision also recorded that Jian’s bid was approximately 14.2 per cent lower than KVR’s, but both received full marks for price. The panel made clear that identical price scores were not, on their own, proof of a breach. The unlawful step was the use of an undisclosed evaluation method.
The panel ordered T&TEC to terminate the procurement on August 14 and pay Jian $42,337.50 in costs. Its written reasons said there was insufficient evidence to establish the challenger’s allegations of bias or a deliberate attempt to favour KVR.
A pricing test bidders did not know
At Paria Fuel Trading, the disputed procurement was for marine security services.
The company issued a fresh invitation to bid in October 2025, after cancelling an earlier exercise. Bidders were told their prices would be assessed against industry standards.
But Paria’s evaluators used an internal company estimate and undisclosed price bands. Bids closer to that estimate received higher scores. Amalgamated Security Services Limited challenged the process.
The OPR found that Paria had used a method bidders could not have known from the tender documents. The panel said the undisclosed system made the commercial evaluation “procedurally unfair and legally invalid”.
Paria cancelled the procurement on March 27 this year, after the challenge was filed. But the panel ruled that cancellation did not erase the bidder’s right to seek legal costs if a breach had occurred.
The April 28 order required Paria to pay Amalgamated Security Services $36,383.33, representing one-third of assessed legal costs. The written reasons were issued in May.
Latest ruling in Tobago
The most recent decision concerns the TRHA’s tender for consultancy services to implement a quality management system.
J.M. Mercedes Property Management, Consultancy and Contracting Services Limited brought the challenge. In an order dated October 16, the OPR found that the authority breached Sections 5(2) and 30(1)(a) of the Act.
The hearing panel ordered the TRHA to pay the company $44,100 in legal costs by December 16. It dismissed a separate claim for the bidder’s submission costs because that amount had not been proved.
Unlike the three other cases, the OPR’s public register did not contain detailed written reasons for the TRHA ruling. It would therefore be wrong to say the same evaluation-method breach was established in that case.
Changes to the law
There is another issue following the HDC report. On October 9, the Government’s amendments to the procurement law were subsequently published as an Act of Parliament, effectively changing what the OPR can do after certain complaints and investigations.
Under the amended Section 44, the regulator cannot use a Part IV complaint or investigation to order a public body to suspend a tender, re-evaluate bids, overturn a contract or terminate procurement proceedings. Recommendations made under that Part are advisory and not binding.
The changes also exempt qualifying public-private partnerships for public housing from the Act’s procurement requirements.
That has implications for any future decision to retender HDC’s housing packages.
An OPR source said the findings against HDC were supported by the rules governing public procurement. But the source also raised concerns about what the recent amendment means for future housing contracts.
When asked whether the ongoing HDC investigation was now effectively a waste following the procurement amendments, the source replied:
“Well, basically, yes. It could only be based on the amendment to the Act.”
However, the source said the audit was well executed. “And I think based on the findings and the conclusion, it was a well done audit investigation on the circumstances under which these things were awarded.”
The source said that if the cancelled HDC housing packages are put out to tender again under a public-housing public-private partnership, the new exemption could put those contracts outside the OPR’s normal procurement oversight.
The source described the position confronting the regulator in stark terms.
“They are between a rock and a hard place. That’s the OPR in terms of what they can do and what they can’t do.”
The source said the changes would not prevent a separate criminal investigation if evidence of wrongdoing emerged.
“That doesn’t stop the DPP or the police from conducting an investigation if there is any alleged corruption or corrupt practices.”
The source said the amendments do not terminate investigations that began before the law changed.
Efforts to contact Regulator Beverly Khan were unsuccessful.